Bathroom renovation project almost complete. Kayla and I have been working on this for a few weeks.
Weekend 1 was demolition, we removed the vanity, the toilet, the vinyl floor, and the plywood subfloor.
Weekend 2 was the floor, we put down cement board and tiled. One night this week @kaylalabonte grouted the tiles.
Weekend 3 (this weekend) was plumbing, we installed the new toilet and the new vanity.
Just need to finish the baseboard moulding.